Pembangunan MRT Jakarta Capai 95,97 Persen

Phase I MRT Development Reaches 95.97 Percent

Physical development is consisting of elevated station that has reached 94.42 percent, underground station has reached 97.53 percent, and depot and elevated section has reached 94.42 percent

The phase I MRT development that connects Lebak Bulus to HI Roundabout today, has reached 95.97 percent.

"Physical development is consisting of elevated station that has reached 94.42 percent, underground station has reached 97.53 percent, and depot and elevated section has reached 94.42 percent," disclosed MRT Jakarta President Director, William P Sabandar, Tuesday (8/28).

Anies Rides MRT Trains from Lebak Bulus towards HI

If it is calculated with operation time, his party still has 184 days to prepare for any shortcomings.

"Hopefully everything can run smoothly and well," he hoped.

Linked News
Popular News indeks
  1. Jakarta Builds Five New Animal Health Centers to Expand Veterinary Services

    access_time30-09-2026 remove_red_eye495 personAldi Geri Lumban Tobing
  2. Open for All: Jakarta City Hall Welcomes Visitors for Namu Balai Kota

    access_time03-10-2026 remove_red_eye471 personDessy Suciati
  3. Transjakarta Reaffirms Ban on Busking in Mikrotrans and Bus Stops

    access_time02-10-2026 remove_red_eye430 personAldi Geri Lumban Tobing
  4. Buildings on the Sidewalk in Front of Plumpang Transjakarta Bus Stop Demolished

    access_time30-09-2026 remove_red_eye411 personAnita Karyati
  5. Commission D Supports Reserve Fund for Long-Term Infrastructure

    access_time02-10-2026 remove_red_eye397 personFakhrizal Fakhri